BWC070, BWC090, BWC120 Installation Manual Supplement June 12 th , 2007 The following pages are copied from the latest edition of the installation manual for the above boilers, which is not yet in print. These pages cover new vent options that have been added for these boilers and which are not shown in the current manual.
VII V enting W ARNING F AILURE T O VENT THIS BOILER IN ACCORDANCE WITH THESE INSTRUCTIONS COULD CAUSE FLUE GAS T O ENTER THE BUILDING RESUL TING IN SEVERE PROPER TY DAMAGE, PERSONAL INJUR Y , OR DEA TH: * Do not attempt to vent this boiler with galvanized, PVC, or any other vent components not listed in T able 7.
12 2) Maximum V ent and Air Intake Lengths - The maximum length of the vent air intake piping depends upon the vent option selected and the boiler size. See T able 7.1 or 7.9 for the maximum vent length. In horizontal vent systems, the lengths shown in T able 7.
13 T ABLE 7.1: SUMMAR Y OF HORIZONT AL VENTING OPTIONS VENT OPTION # 1 2 3 CLASSIFICA TION USED IN THIS MANUAL HORIZONT AL CONCENTRIC HORIZONT AL TWIN PIPE HORIZONT AL CONCENTRIC ILLUSTRA TED IN FIGURE 7.
14 FIGURE 7.2: HORIZONT AL CONCENTRIC VENTING (VENT OPTION 1,3) FIGURE 7.3: HORIZONT AL TWIN PIPE VENTING (VENT OPTION 2).
15 T ABLE 7.4a: CROWN CONCENTRIC 60/100 VENT COMPONENTS (VENT OPTION 1) CROWN PN DESCRIPTION SIZE USED ON VENT OPTION # COMMENTS 230521 80/125 x 60/100mm REDUCING ELBOW 80/125 x 60/100mm 1 INCLUDED WI.
6) Permitted T erminals for V ertical V enting - • V ent Option 5 - A straight termination is installed in the end of the vent pipe. V ent manufacturer part numbers for these screens are shown in T able 7.5. The air inlet terminal consists of a 180 degree elbow (or two 90 degree elbows) with a rodent screen as shown in Figure 7.
FIGURE 7.6a: LOCA TION OF VENT TERMINAL RELA TIVE TO WINDOWS, DOORS, GRADE FIGURE 7.6b: LOCA TION OF VENT TERMINAL RELA TIVE TO METERS AND FORCED AIR INLETS FIGURE 7.
18 9) Pitch of Horizontal Piping - Pitch all horizontal piping so that any condensate which forms in the piping will run towards the boiler: • Pitch Crown horizontal concentric venting 5/8” per foot • Pitch Stainless steel venting 1/4” per foot.
19 T ABLE 7.9: SUMMAR Y OF VER TICAL VENTING OPTIONS VENT OPTION # 5 6 CLASSIFICA TION USED IN THIS MANUAL VER TICAL TWIN PIPE VER TICAL CONCENTRIC ILLUSTRA TED IN FIGURE 7.
20 FIGURE 7.10: VER TICAL TWIN PIPE VENT SYSTEM (VENT OPTION 5) FIGURE 7.1 1: VER TICAL CONCENTRIC VENT SYSTEM (VENT OPTION 6).
B. Removing an Existing Boiler From a Common Chimney Read this only if the BWC boiler is replacing an existing boiler that is being removed from a common chimney .
22 C. Assembly of Crown 60/100mm Concentric V enting (IMPOR T ANT - Skip to Section D for 80/125mm Concentric V ent Assembly) W ARNING Failure to follow the instructions could r esult in flue gas leakage into the combustion air or indoor air , resulting in unsafe or unr eliable operation.
FIGURE 7.21: DIMENSION “L” 23 FIGURE 7.20: INST ALLA TION OF REDUCING ELBOW ON CONCENTRIC BOILER COLLAR.
24 6) Use locking bands provided to join adjacent sections of non-cuttable pipe as well as fittings. The male end of the terminal section and other cuttable sections must be held to the female end of the adjoining pipe with at least three #10 x 1/2” sheet metal screws.
FIGURE 7.25: A TT ACHING 60/100mm TERMINAL SECTION 25 FIGURE 7.24: PREP ARING 60/100mm TERMINAL SECTION FOR INST ALLA TION IN THE W ALL.
D. Assembly of Crown 80/125mm Concentric V enting (IMPOR T ANT - See Section C for 60/100mm Concentric V ent Assembly) W ARNING Failure to follow the instructions could r esult in flue gas leakage into the combustion air or indoor air , resulting in unsafe or unr eliable operation.
T o cut the straight sections listed above refer to Figure 7.31 and the following instructions: a) Determine the required length of the outer pipe. When doing this allow an additional 1” of length for insertion into the female end of the adjoining pipe.
3) Joining Pipe - a) Start assembly of the vent system at the boiler . Lubricate the brown gasket in the boiler vent collar with a few drops of water .
4) 80/125mm Horizontal T erminal Installation - a) Cut a 5-1/2” diameter hole through the exterior wall at the planned location of the horizontal terminal. b) Measure distance “L” from the outside surface of the exterior wall to the end of the last fitting as shown in Figure 7.
FIGURE 7.33c: CUTTING INNER PIPE OF 80/125mm HORIZONT AL TERMINAL FIGURE 7.33d: COMPLETING 80/125mm HORIZONT AL TERMINAL INST ALLA TION 30.
5) Snorkel T erminal Installation - The Snorkel Kit (PN 230540) consists of the following (Also see Figure 7.34): Key # Part # Description 1 230541 Support Elbow 2 230542 Lower W all Bracket 3 230543 .
d) Complete the vent system inside the structure. The support elbow sits on the M10 x 35 screw as shown in Figure 7.34. Cut the W all Penetration Section to the length required to connect the interior vent system to the Support Elbow following the instructions on Page 26.
FIGURE 7.35b: CUTTING VER TICAL TERMINAL FIGURE 7.35c: COMPLETING VER TICAL TERMINAL INST ALLA TION 33.
FIGURE 7.36: CHIMNEY CHASE INST ALLA TION 7) Chimney Chase Installation - A vertical 80/125mm vent system can be installed in an unused masonry chimney . This installation is similar to other vertical installations with the following exceptions (Also see Figure 7.
CAUTION V ent systems made by Heat Fab, Protech, Z-Flex, and Metal-Fab rely on gaskets for proper sealing. When these vent systems are used, take the following precautions: • Make sure that gasket is in position and undamaged in the female end of the pipe.
36 3) Assembly of Metal-Fab Corr/Guard V ent System: a) Corr/Guard General Notes: • Do not cut Corr/Guard vent components. • Refer to Corr/Guard installation instructions for proper methods of support. • Orient Corr/Guard components so that the males ends of all fittings point in the direction of the boiler .
デバイスCrown Boiler BWC070の購入後に(又は購入する前であっても)重要なポイントは、説明書をよく読むことです。その単純な理由はいくつかあります:
Crown Boiler BWC070をまだ購入していないなら、この製品の基本情報を理解する良い機会です。まずは上にある説明書の最初のページをご覧ください。そこにはCrown Boiler BWC070の技術情報の概要が記載されているはずです。デバイスがあなたのニーズを満たすかどうかは、ここで確認しましょう。Crown Boiler BWC070の取扱説明書の次のページをよく読むことにより、製品の全機能やその取り扱いに関する情報を知ることができます。Crown Boiler BWC070で得られた情報は、きっとあなたの購入の決断を手助けしてくれることでしょう。
Crown Boiler BWC070を既にお持ちだが、まだ読んでいない場合は、上記の理由によりそれを行うべきです。そうすることにより機能を適切に使用しているか、又はCrown Boiler BWC070の不適切な取り扱いによりその寿命を短くする危険を犯していないかどうかを知ることができます。
ですが、ユーザガイドが果たす重要な役割の一つは、Crown Boiler BWC070に関する問題の解決を支援することです。そこにはほとんどの場合、トラブルシューティング、すなわちCrown Boiler BWC070デバイスで最もよく起こりうる故障・不良とそれらの対処法についてのアドバイスを見つけることができるはずです。たとえ問題を解決できなかった場合でも、説明書にはカスタマー・サービスセンター又は最寄りのサービスセンターへの問い合わせ先等、次の対処法についての指示があるはずです。